How Long Does a Basement Finish Take?
- Torey Hughes
- Sep 22
- 2 min read

One of the first questions homeowners ask us is: “How long will it take to finish my basement?” It’s a great question—and the honest answer is: it depends. Every basement is unique, and the timeline can vary based on design choices, size, and complexity. Still, most basement finishes fall into a predictable range.
Typical Timeline for a Basement Finish
1. Planning & Design (2–4 weeks)
Before construction begins, there’s a planning stage. This includes discussing your vision, creating layouts, making selections for finishes, and finalizing the contract.
2. Permits & Approvals (1–3 weeks)
Depending on your location, permits may be required for electrical, plumbing, or structural changes. This step can add time but ensures everything is safe and up to code.
3. Framing & Rough-Ins (2–3 weeks)
Framing defines the layout of your new space. During this stage, electricians, plumbers, and HVAC professionals also “rough in” the essential systems behind the walls.
4. Drywall, Flooring & Finishes (3–5 weeks)
Once inspections are complete, it’s time to bring the space to life. Drywall goes up, floors are installed, trim is added, and painting is completed. Custom features like bars, saunas, or built-ins may extend this step.
5. Final Touches & Walk-Through (1 week)
Lighting, hardware, and décor are added. A final walk-through ensures everything meets your expectations.
Average Total Time: 8–12 weeks
On average, most basement finishes take about two to three months from start to finish. Larger, more complex designs (like adding bathrooms, custom tile work, or wet bars) can extend the timeline.
Why Timelines Matter
A clear schedule helps set expectations and reduces stress for homeowners. At Mandolin Rising Construction, we keep you updated at every stage so you know exactly what’s happening in your home.
Thinking about finishing your basement? Let’s talk about your timeline and bring your vision to life.